Project Purpose

The Boston Water and Sewer Commission’s (BWSC) Back Street Project involves sewerage and drainage improvements that include replacement and lining of existing sewers and storm drains.   The purpose of this project is to replace or rehabilitate cracked and broken pipe that has the potential to lower the groundwater table. 

The BWSC wants to ensure that when groundwater levels do rise because of the improvements to other agencies’ facilities, that any sewers and drains owned by the BWSC are in excellent condition, and will not cause future groundwater lowering.

Community Relations

BWSC is committed to a proactive community relations program. The program is designed to keep residents, businesses and elected officials informed about the project by holding public meetings, listing details of the project on BWSC’s website, and meeting with community groups and elected officials, as requested. In addition, before construction begins, a notice will be mailed announcing the work to be performed on the street. Any questions may be directed to Tom Bagley, Manager of Community Services, at 617-989-7000.

Scope of Work

Back Street – Embankment Road to Exeter Street:  Work on this section includes the replacement of approximately 4,650 linear feet of sanitary sewer and storm drain pipes, ranging in size from 12–inch to 18-inch, and installation of approximately 1,300 linear feet of drainage galley.

Back Street - Exeter Street to Massachusetts Avenue:  Work on this section includes the structural lining of approximately 2,750 linear feet of existing sewer and storm drain pipes, ranging in size from 8-inch to 18-inch.

Project Area

The Back Street Project area is generally defined from Embankment Road to Massachusetts Avenue.

Project Coordination and Construction Activity

BWSC is committed to working closely with the Mayor’s Office, Boston Transportation Department, elected officials, building owners, superintendents and trustees. Effective project coordination will also help mitigate many of the short-term construction related impacts that will be associated with the project.

All dust, debris and excavate will be strictly controlled and monitored. In an effort to streamline and expedite all temporary and permanent roadway resurfacing activity, BWSC will complete all pavement restoration work as part of this project.
 

PROJECT CONTACTS

For more information on the project, or to be added to the mailing list, please contact us.

John Baulds, Project Manager, D’Allessandro jbauld@dallessandro.com

Steven Callaghan,
BWSC Deputy Director of Construction,
617-989-7438

Irene McSweeney Woodfall,
BWSC Director of Construction,
617-989-7447

Thomas Bagley,
BWSC Manager of Community Services,
617-989-7000

Torrey LeCornec
Parking Coordinator, D'Allessandro Corp.
617-413-2121
tlecornec@dallessandro.com
 

 

To receive email notices outlining the work to be done and how you will be affected, join the Back Street Project E-List by completing the form below.

Name   Phone
Address   Email  

Check One

Resident      Building Supervisor/Trustee/Owner