Site Navigation

Customer Login

Need help logging in?

Did You Know?

The illegal operation of fire hydrants is dangerous and can result in breaks and the malfunction of the hydrant when needed for fire emergencies. Keep neighborhoods safe; report open hydrants to 617-989-7000.

Back Bay Water, Sewer and Drainage Project

Back Bay
Back Bay

Purpose

This project includes the structural lining of 430 feet of combined sewer and the rehabilitation of 3 manholes in Fairfield Street. Work will be done in two phases and is expected to cause noise, dust, delays and modifications to traffic and parking.

Project Updates
12/1/2017 BACK BAY DECEMBER 2017
11/3/2017 BACK BAY NOVEMBER UPDATE

Scope of Work

Work under this contract includes the structural lining of the 70"x72" combined sewer and manholes in Fairfield Street. The liner will address groundwater infiltration in the sewer and manholes.

What to Expect

  • Modifications to traffic and parking
  • Construction noise, dust and delays
  • Cleaning and television inspection of the sewer
  • Excavation of access holes to install the sewer liner
  • Installation of sewer by-pass pumps and piping
  • Restriction to water use
  • Odor from structural liner installations and by-pass
  • The liner installation is a continuous process and will need to take place over a 36 hour period.

Anticipated Impacts

The anticipated impacts include water service interruptions, noise, traffic and parking modifications, rodent activity, dust and general construction impacts. The contractor will be required to minimize impacts to the extent feasible.

Surface Restoration

Temporary restoration of roadways, sidewalks and other areas disturbed by construction will be completed under this contract. Permanent restoration will occur under a separate paving contract. Concrete or Brick sidewalks will be restored within six weeks, weather dependent.

Overall Schedule

  • October 2017 to December 2017

Project Coordination and Construction Activity

The Commission is committed to working closely with the Mayor's Office: elected officials; Boston Public Works Department (BPWD), Boston Transportation Department (BTD), and other City departments; other public and private utility companies; state and federal regulatory agencies; and, most importantly, with abutters to ensure the project is successfully completed. Effective coordination will also help mitigate many short-term construction related impacts that may be associated with the project.

Community Relations Program

The Commission is committed to a proactive community relations program during construction of this project. The program is designed to keep residents, businesses and elected officials informed about the project by holding public meetings, placing notices in local newspapers and posting updates on the project webpage, which will be available on the Commission's website at: BWSC.org

Before construction begins on a section of the street, a notice will be sent in the mail. The contractor is required to provide 48-hour notice to abutters for any anticipated water interruptions. Advisories and periodic updates and notices will be distributed to the project email list and on the Commission's website. Project staff will meet periodically with residents, businesses, civic groups, and elected officials to provide updates, as requested or appropriate.

Commission staff will work closely with affected abutters regarding issues such as pedestrian and vehicular traffic management, access to residences and business establishments, and maintaining access for deliveries and trash removal. The Commission will coordinate access and water interruptions with individual businesses and property owners/managers affected by any water main replacements.

During construction hours, a full-time Inspector will be onsite. To ensure a timely response, any concerns or questions should be addressed to field personnel. Contact the BWSC Inspector onsite or at the phone numbers listed in the Project Contacts box to the right.

In the event of an emergency during non-work hours, please contact the Commission for the fastest response at: 617-989-7000.

Please keep this notice for the relevant contact information.

Contacts

If you have questions or concerns about construction, please contact:

Boston Water and Sewer Commission - 617-989-7000

Irene McSweeney, Director of Construction, 617-989-7447

BWSC Project Engineer - Peter Salvatore - 617-989-7363


Dolores Randolph - Deputy Director of Communications, 617-989-7360


Contractor Contacts

Paul Umbro - Project Manager - Umbro & Sons Construction - 857-492-7260


In an emergency, contact BWSC's 24-hour, 7-day a week number at 617-989-7000.

Footer