As work under this contract progresses, RJV Construction will be required to tie-in the sewer and drain on Clifford Street into the new sewer and drain installed in Blue Hill Ave. Because of the depth and location of these pipes, traffic flow onto Clifford Street from Blue Hill Ave cannot be safely maintained and will be blocked. This work is scheduled to start on April 8th and is anticipated to be complete on April 19th. Work will take place between 9AM and 3PM.